Tuesday, March 22, 2011

The Crew is almost done with Phase 1

 The tin is flying this morning!
 The interior posts are placed!
 The concrete crew is leveling the floor! Had a minor setback here! The construction crew wasn't aware of the heated flooring so much of the rock pad had to be removed!
 The windows look great! Couldn't have matched the color any better if we had ordered them! Craigslist...what a wonderful thing!
 Since the concrete crew is on site..we had to adjust the walkway too! Glad we have been on site everyday to catch the little things that will make us much happier in the long run!
 Here is the "living quarters" side! Wow..it looks like alot of space!
 And here is the rock that had to be removed! Almost as much as we had for just in case! A little frustrated..but at least it will be right!
 The North side in completely covered!
And most of the West side! We had a minor setback yesterday with the wind catching one of the windows before it was installed and breaking! So, this morning Stacie took the broken one back to the city and picked up the one we had broken when we bought them!