The first of 4 trenches is all but filled. This one is for future utilities! The two pipes will be stubbed into the utility room for "just in case".
We made some great progress on the sewer lines! The one to the far left is for the washer, then the rear one is for the drain in the utility room, the middle is for the shower, and the front will go to the sink in the shop!
This is the outside of the 4th trench! For some reason, there wasn't a picture of the hole Stacie dug! But it goes all the way beyond the form board! At least one down, only 3 to go! Jason says I am only good for one trench a day! ..WORN OUT!
This is the trench for the water coming in! We put some sand in the bottom to stretch our pex from the well and to lay a line for future water district hook up if we decide to do so! The path to the left goes into the utility room!
The drain boxes are placed! They go across the front of the garage part! Don't want to fill them in just yet, we need to double check on the concrete level and make sure the hoist isn't too low!